As we are in process of shutting down and clearing the area for the Xmas period, I thought a brief update might be in order:

Gowanlea Rd / Strathview Tce area is complete except for some grass reinstatement which will need to wait until springtime.

Dalginross largely complete but some services and side streets are still to be connected to the new main, primarily between Barrack Road and the bridge.

Barrack Road will be closed to traffic on our return from holiday to allow open cut mainlaying here. Residents vehicle access will be available out of hours, and the teams will accommodate daytime access whenever possible. Pedestrian access will not be affected.

South Crieff Road and Braco Road will follow on from Barrack Road.